CALL 24 HOURS IN ADVANCE FOR INSPECTIONS
(All Sub-Trades Must Obtain Pepper Pike Contractor's License and permit if required).
After the building permit has been issued, the contractor has the responsibility of assuring that all required inspections are requested and that any variations from the approved plans are submitted and re-approved prior to making the change.
Only when the permit is displayed and the approved plans are present shall the Inspector perform the inspection.
Each individual subcontractor or the job superintendent must be present during the required inspections. If no one is available, the inspection must be rescheduled.
Required inspections shall be requested by the contractor or his subcontractor a minimum of twenty-four (24) hours before the inspection is needed.
Required inspections are:
- FOOTING INSPECTION: Shall be made prior to the pouring of any concrete footing. (Trench, forms and any reinforcing shall be in place at the time of inspection.)
- FOUNDATION INSPECTION: Shall be made prior to the pouring of foundation walls or piers if reinforcing (rebar) is present. (Reinforcing shall be in place at the time of inspection.) If reinforcing is not required then this inspection shall be made prior to the backfilling of foundation wall or piers. Foundation coatings and drainage tile shall be in place, when needed, at the time of inspection.
- STRUCTURAL INSPECTION: Shall be made after completion of structural work, before any insulation, drywall, lathe, or paneling, etc., is applied, but after any required plumbing, electrical and/or heating rough-in inspections have been approved. All framing shall have been completed with firestops, collar ties, bridging and nailers in place.
- ROUGH PLUMBING INSPECTION: Shall be made after installation of sanitary and/or storm drainage systems. Multiple inspections can be made if systems are installed in sections. Domestic hot and cold water pipe systems will also hold an air test.
- FINAL PLUMBING INSPECTION: Shall be made after all plumbing fixtures have been installed and supplied with domestic hot and cold water and while under final air test.
- ELECTRICAL SERVICE: Must be installed per The Illuminating Company specifications and the National Electrical Code.
- ROUGH ELECTRIC INSPECTION: Shall be made after completion of electrical rough-in prior to covering any wiring.
- FINAL ELECTRICAL INSPECTION: Shall be made after installation of all electrical equipment and/or fixtures.
- ROUGH HEATING INSPECTION: Shall be made after completion of heating rough-in prior to concealment.
- FINAL HEATING INSPECTION: Shall be made after completion of the installation of the heating system and in firing condition.
- FINAL BUILDING INSPECTION: Shall be made after completion of all construction with gutters, splash blocks, handrails, attic access panels, vapor barriers, etc., in place and prior to occupancy.
- FINAL GRADE AND LANDSCAPING: Shall be made after completion of final contouring and planting of nursery stock and conforms to the approved landscape plan submitted previously. Compliance with the tree ordinance of the City will be verified at this time.
Any work which does not meet the standards contained in the Pepper Pike Code of Building Regulations shall be corrected within a reasonable time specified by the Building Inspector or his authorized representative. A re-inspection shall then be made at no additional fee.
When all inspections are completed and approved, a Certificate of Occupancy will be issued. Occupancy shall not take place prior to the issuance of the Certificate.